calldocumentfacebookmessagemypartnerwindowsapplegoogleplayworkerroutecoinspinterestplaysearchsmartphonetwittercaraccordeonvideoarrowarrowdownloaddownloaduploadsection_scrollerglobemapIcon-Shop-Websitecontactenergyhomebridgeshighrisetunnelmininghousearrow-uparrow-downarrow-leftarrow-leftarrow-circle-rightchevron-right-circleuserexternlinkcartissuuclosekeystarweb

Shimizu Corporation, Head Office

Japan

Construction major Shimizu Corporation used Doka Automatic climbing formwork SKE 50 plus to erect the structure core of its new Head Office building. This made it possible to greatly shorten the build-time, as it took only two to three days to cast each storey, and around two months to complete 18 storeys.

Back

Project data

Year of completion
2012
Country
Japan
Address
2 Kyobashi, Chuo-ku, Tokyo
Postcode
104-0031
Town or city
Tokyo
Realization
Shimizu Corporation
Structure
Office/administration/multipurpose building
Type of structure
High-rises

Shaft / core

Construction method
Core formed/poured in advance
Number of storeys
21
Structure height
106 m m
Cycle time
6 -day cycle