The 35-storey office building is refurbished, while its podium is replaced with a new 50-storey five-star hotel with 700 rooms which located strategically at Jalan Sultan Ismail, Kuala Lumpur. Doka supplied formwork for the entire project. With the requirement of 6 days cycle time with high safety standard, Doka supplied X-climb 60 for corewall to jump ahead. Due to limited cranage available at site, table lifting system (TLS) has greatly overcome the challenge to move Dokaflex table without crane. As the site is located next to the heavy traffic, Protection Screen X-Climb 60 is used to prevent falling objects.
Challenge:
Site with limited space and congested.
Surrounded by office/highrise buidings.
Heavy traffic.
Hence, required a high safety standard with 6 days cycle time
Solution:
Proposed using X-climb 60 corewall to jump head to save the cycle time . X-climb 60 pretection screen for safety protection and using dokaflex table form with table lifting system to reduce the crane usage.
Year of completion
2018
Country
Malaysia
Zip/Postal Code
50450
City
Kuala Lumpur
Contractors
Ahmad Zaki Sdn Bhd
Structure height
250 m
Height of casting sections
3,6
floors
50
net area
103666
Cycle time
7