calldocumentfacebookmessagemypartnerwindowsapplegoogleplayworkerroutecoinspinterestplaysearchsmartphonetwittercaraccordeonvideoarrowarrowdownloaddownloaduploadsection_scrollerglobemapIcon-Shop-Websitecontactenergyhomebridgeshighrisetunnelmininghousearrow-uparrow-downarrow-leftarrow-leftarrow-circle-rightchevron-right-circleuserexternlinkcartissuuclosekeystarweb

Brenner Railway, H4-3 Stans

Austria

As part of the upgrading of the Brenner railway transit corridor, Alpine Bau was appointed to build the tunnel in 'Contract section H4-3 Stans'. Doka supplied an all-hydraulic tunnel formwork traveller for constructing a 655 m long section of tunnel using the cut-and-cover method.

Back to the overview

Project data

Year of completion
2008
Project duration
20 Months
Country
Austria
Town or city
Stans
Realization
Alpine Bau GmbH
Structure
Tunnel
Type of structure
Cut-and-cover tunnel

Wall

Construction method
Partially monolithic
Cross-sectional shape
Curved/round
Clear width
11.40 m
Clear height
8.60 m
Formed length of tunnel
655 m
Parapet height
0.70 m
Length of concreting section
10 m
Number of casting sections
67
Cycle time
7 -day cycle