calldocumentfacebookmessagemypartnerwindowsapplegoogleplayworkerroutecoinspinterestplaysearchsmartphonetwittercaraccordeonvideoarrowarrowdownloaddownloaduploadsection_scrollerglobemapIcon-Shop-Websitecontactenergyhomebridgeshighrisetunnelmininghousearrow-uparrow-downarrow-leftarrow-leftarrow-circle-rightchevron-right-circleuserexternlinkcartissuuclosekeystarweb

Cable-stayed bridge over River Tajo

Spain

The 180 m tall, 68°-angled single pylon of the cable-stayed bridge across the River Tajo was constructed using the versatile Doka automatic climbers SKE100 and Doka large-area formwork Top 50.

Back to the overview

Project data

Year of completion
2011
Project duration
20 Months
Country
Spain
Town or city
Talavera de la Reina
Realization
UTE Ronda Sur Talavera (Sacyr + Aglomancha + Jesús Bárcenas)
Structure
Bridge
Type of structure
Piers and pylons

Pylon

Construction method
Inclined
Structure height
180 m
Height of casting sections
3 m
Number of casting sections
62
Cycle time
4 -day cycle