calldocumentfacebookmessagemypartnerwindowsapplegoogleplayworkerroutecoinspinterestplaysearchsmartphonetwittercaraccordeonvideoarrowarrowdownloaddownloaduploadsection_scrollerglobemapIcon-Shop-Websitecontactenergyhomebridgeshighrisetunnelmininghousearrow-uparrow-downarrow-leftarrow-leftarrow-circle-rightchevron-right-circleuserexternlinkcartissuuclosekeystarweb

Tech Gate Tower

Austria

Right next-door to Vienna's UNO-City, this 20-storey high-rise complex provides spacious office facilities to more than 30 high-tech companies. Thanks to the Doka formwork solution, the fast cycle times required on this build were accomplished to perfection.

Back to the overview

Project data

Year of completion
2005
Project duration
6 Months
Country
Austria
Address
Donau-City-Strasse 1
Postcode
1220
Town or city
Vienna
Realization
Strabag Direktion AP, Vienna
Structure
Office/administration/multipurpose building
Type of structure
High-rises

Shaft / core

Construction method
Core formed/poured in advance
Number of storeys
20
Structure height
75 m
Height of casting sections
3.44 m
Number of casting sections
19
Cycle time
7 -day cycle

Floor-slab

Construction method
Straight
Number of storeys
20
Structure height
75 m
Height of casting sections
3.44 m
Number of casting sections
19
Cycle time
7 -day cycle