calldocumentfacebookmessagemypartnerwindowsapplegoogleplayworkerroutecoinspinterestplaysearchsmartphonetwittercaraccordeonvideoarrowarrowdownloaddownloaduploadsection_scrollerglobemapIcon-Shop-Websitecontactenergyhomebridgeshighrisetunnelmininghousearrow-uparrow-downarrow-leftarrow-leftarrow-circle-rightchevron-right-circleuserexternlinkcartissuuclosekeystarweb

Gyermelyi Tésztagyár Zrt. Malomépítés

Hungary

In 2013 GAG Gyermely completed a new milling operation with a daily capacity of 200 tonnes soft and 150 tonnes durum wheat. The two billion HUF investment results in further strengthening the market leader position of the plant and increased its already significant milling capacity. To finalise the investment economically and precisely, Magyar Doka Zsalutechnika Kft. (Hungarian Doka Formwork Technology LLC) delivered its various formwork and safety systems. In addition it provided its experience and expertise, thereby ensuring successful implementation of the construction project.

Back

Project data

Year of completion
2013
Project duration
3 Months
Country
Hungary
Address
Bajnai út 1.
Postcode
2821
Town or city
Gyermely
Realization
Tótok és Fiai Kft. (Tótok and Sons)
Structure
Production facility / industrial building
Type of structure
Industrial structures

Shaft / core

Construction method
Monolithic
Number of casting sections
57