HRSB Infrabina Sdn Bhd undertook the construction of storage silo tanks consisting of several large tanks with three castings each. The primary objectives were to prevent thermal cracks and optimise the formwork cycle while ensuring the highest standards of concrete quality. The real-time monitoring with #Concremote enabled our customer to find the perfect time for stripping based on reliable records and thus save 42 % in stripping time.
Time to target strength value reduced by 42% (4 days instead of 7 days)
Formwork removal at the right strength enhanced safety
Reliable records of “as-built” data
Minimised risk of thermal cracks in the concrete
Reduction of crack repair measures
Cost reduction due to optimisation of formwork use on site
Year of site completion
2023
Country
Malaysia
City
Malacca City
Postal Code
78300
Period of Concremote use
from 10|2022 on
Customer
HRSB Infrabina Sdn Bhd
Type of Construction
Storage Silo (Water tanks)
Used Concremote hardware
Calibration box, cable sensors 2.0
Concrete mixes in use
1
Number of measurements:
10+