calldocumentfacebookmessagemypartnerwindowsapplegoogleplayworkerroutecoinspinterestplaysearchsmartphonetwittercaraccordeonvideoarrowarrowdownloaddownloaduploadsection_scrollerglobemapIcon-Shop-Websitecontactenergyhomebridgeshighrisetunnelmininghousearrow-uparrow-downarrow-leftarrow-leftarrow-circle-rightchevron-right-circleuserexternlinkcartissuuclosekeystarweb

Precast plant OBERN­DORFER

Gunskirchen, Austria

Safe and earliest possible pre-tensioning of precast concrete elements with real-time concrete monitoring

Since 2018, the Austrian precast producer OBERNDORFER has been relying on real-time concrete monitoring with Concremote in the production process for beams and columns. The curing process of the concrete is monitored by sensors and the data is provided in real time. This enables reliable decisions to be made about the earliest possible stripping time. This will also be of great importance in the future when working with CO2-reduced concrete mixes, as OBERNDORFER wants to focus on more environmentally friendly production by selecting the most suitable type of concrete. The automatic, digital documentation of measurement data for quality assurance, which guarantees transparency in the production process, is also particularly important to the precast company.

Customer requirements:

  • Safe pre-tensioning of precast columns and trusses
  • Documentation

Concremote solution:

  • Concremote calibration to calibrate the concrete recipes and, if necessary, alternative mixes.
  • Concremote slab sensors 2.0 are used in production, which are customised with a flat measuring point.
  • Documentation for quality assurance
Time savings

Time savings

Up to 90 minutes earlier post-tensioning of precast elements.

More safety

More safety

Safe pre-tensioning or lifting of the finished parts when the required strength is reached.

Enhance Quality

Enhanced concrete quality

Automatic Concremote reports for quality assurance.

Project data

Country
Austria

City
Gunskirchen

Postcode
4623

Period of Concremote use
03/2018 - ongoing

Customer
FRANZ OBERNDORFER GmbH & Co KG


Building data

Type of construction
Precast elements - precast plant

Concremote

Used Concremote hardware:
slab sensors 2.0 (special sensors with flat measuring point) 2 pcs. calibration boxes 2.0

Concrete mixes in use:
C30/37 to C50/60 (depending on component)

Number of measurements:
1.500 and still counting

Systems used

Services used

Stefan Scheuchelbauer

Would you like to get to know the potential of Concrete Monitoring at your next construction project?

Get in touch with our experts!

Fields marked with * are required.
* Please fill out all required fields!
    Message could not be sent – please try again a little later!