calldocumentfacebookmessagemypartnerwindowsapplegoogleplayworkerroutecoinspinterestplaysearchsmartphonetwittercaraccordeonvideoarrowarrowdownloaddownloaduploadsection_scrollerglobemapIcon-Shop-Websitecontactenergyhomebridgeshighrisetunnelmininghousearrow-uparrow-downarrow-leftarrow-leftarrow-circle-rightchevron-right-circleuserexternlinkcartissuuclosekeystarweb
I consent to the use of cookies by this website for analyses and personalised content. Find out more OK
I consent to the use of cookies by this website for analyses and personalised content. Find out more OK

Wood Wharf A2 A3

London, United Kingdom

Kilnbridge Construction Services Limited select Doka for their formwork requirements at Wood Wharf A2 / A3 - soon to be Canary Wharf's first ever residential development. The scope of works involves the construction of the common basement and medium to high-rise structures with an overall RC footprint of over 65,000m2. Building A2 comprises of 14 floors and Building A3 comprises a further 44 floors of concrete frame. Altogether, Buildings A2 and A3 comprise 5,600 tonnes of reinforcement, 31,000m³ of concrete and 65,200m² of soffit formwork.

Solution:
Automatic climbing formwork SKE 50 plus
Automatic climbing formwork Xclimb60
Staxo Suspended Stair Tower 250
Framed formwork Framax Xlife

Back to overview

Project data

Year of completion
RC Frame June 2018
Project duration
RC Frame 96 weeks
Country
United Kingdom
City
Canary Wharf, London
Contractor
Kilnbridge Construction Services Limited

Building data

Shaft / Core

Construction method
Core ahead
Number of storeys
44
Structure height
158.40 m
Height of casting sections
3.285 m
Number of casting sections
43
Cycle time
8 days (currently completing in 6 days)

Wall

Construction method
Doka Framax Xlife panels
Structure height
3.3. m foor to floor
Height of casting sections
3.3 m