calldocumentfacebookmessagemypartnerwindowsapplegoogleplayworkerroutecoinspinterestplaysearchsmartphonetwittercaraccordeonvideoarrowarrowdownloaddownloaduploadsection_scrollerglobemapIcon-Shop-Websitecontactenergyhomebridgeshighrisetunnelmininghousearrow-uparrow-downarrow-leftarrow-leftarrow-circle-rightchevron-right-circleuserexternlinkcartissuuclosekeystarweb
I consent to the use of cookies by this website for analyses and personalised content. Find out more OK
I consent to the use of cookies by this website for analyses and personalised content. Find out more OK

Palms

United States of America

A brutally tight timetable for the project to enlarge the famous Palms Casino & Hotel complex in Las Vegas with a new 140 m tower prompted contractors Isaac Construction to bank on automatic climbing technology from Doka USA.

Back

Project data

Year of completion
2006
Project duration
10 Months
Country
United States of America
Address
4321 West Flamingo Road
Town or city
Las Vegas
Contractors
Isaac Construction
Structure
Hotel
Type of structure
High-rises

Shaft / core

Construction method
Wall with slab/panel
Number of storeys
29
Structure height
140 m
Height of casting sections
2.84 m
Number of casting sections
39
Cycle time
3 -day cycle