calldocumentfacebookmessagemypartnerwindowsapplegoogleplayworkerroutecoinspinterestplaysearchsmartphonetwittercaraccordeonvideoarrowarrowdownloaddownloaduploadsection_scrollerglobemapIcon-Shop-Websitecontactenergyhomebridgeshighrisetunnelmininghousearrow-uparrow-downarrow-leftarrow-leftarrow-circle-rightchevron-right-circleuserexternlinkcartissuuclosekeystarweb

A12 Senftenberg Gallery Refurbishment

Austria

In a first, Doka is fielding a formwork traveller with a face-sheet made of steel panels to produce a new inner shell for the twin-tube Senftenberg Gallery. Following 36 casting sections in the1st tube and a break to accommodate winter tourist travel, the same forming traveller can be re-used for the 2nd tube with only minor modification.

Back

Project data

Year of completion
2015
Project duration
7 Months
Country
Austria
Postcode
6491
Town or city
Schönwies
Realization
Strabag AG
Structure
Tunnel
Type of structure
Mining-type tunnel

part-monolithic

Cross-sectional shape
Curved/round
Clear width
10.0 m
Clear height
6.5 m
Formed length of tunnel
360 m
Length of concreting section
10.0 m
Number of casting sections
36 per tube
Cycle time
2 -day cycle