calldocumentfacebookmessagemypartnerwindowsapplegoogleplayworkerroutecoinspinterestplaysearchsmartphonetwittercaraccordeonvideoarrowarrowdownloaddownloaduploadsection_scrollerglobemapIcon-Shop-Websitecontactenergyhomebridgeshighrisetunnelmininghousearrow-uparrow-downarrow-leftarrow-leftarrow-circle-rightchevron-right-circleuserexternlinkcartissuuclosekeystarweb

City Tunnel, Leipzig, blocks: 36-37

Germany

The City Tunnel project in Leipzig is one of the biggest inner-city infrastructure projects anywhere in Germany. It is part of a large-scale rearrangement of the entire railway system in the Leipzig metropolitan area. In order to deal with the high slab loads and to reduce repositioning times, the Doka heavy-duty supporting system SL-1 was fielded here. Following completion of blocks 36 - 37, most of the items used here were re-used on the tunnel slab traveller for blocks 38 - 44.

Back

Project data

Project duration
1 Months
Country
Germany
Realization
Leipzig City Tunnel consortium
Structure
Tunnel
Type of structure
Cut-and-cover tunnel

Segmented (non-monolithic) casting

Cross-sectional shape
Rectangular
Clear width
4.40 m
Clear height
7.00 m
Formed length of tunnel
27 m
Length of concreting section
13.5 m
Number of casting sections
2