calldocumentfacebookmessagemypartnerwindowsapplegoogleplayworkerroutecoinspinterestplaysearchsmartphonetwittercaraccordeonvideoarrowarrowdownloaddownloaduploadsection_scrollerglobemapIcon-Shop-Websitecontactenergyhomebridgeshighrisetunnelmininghousearrow-uparrow-downarrow-leftarrow-leftarrow-circle-rightchevron-right-circleuserexternlinkcartissuuclosekeystarweb

Viaducto 5

Spain

As part of the project to extend the motorway around the Spanish island of Gran Canaria, Doka supplied all the equipment needed for casting the piers and bridge superstructure of Viaducto 5, in the northern part of the island. As well as the Doka cantilever forming traveller, a newly developed system of main support girders was also fielded on this project, for casting the pier-heads.

Back

Project data

Year of completion
2010
Project duration
21 Months
Country
Spain
Address
Pagador, Gran Canaria
Realization
UTE GUIA-Pagador, OHL
Structure
Bridge
Type of structure
Cantilevering

Piers

Construction method
Conical
Structure height
99 m
Height of casting sections
5 m
Number of casting sections
20
Cycle time
4 -day cycle

Bridge deck/superstructure

Construction method
Straight
Cross-sectional shape
Single-cell box girder – straight webs
Overall length of bridge
432 m
Longest span
114.5 m
Number of piers
4
Number of casting sections
94