calldocumentfacebookmessagemypartnerwindowsapplegoogleplayworkerroutecoinspinterestplaysearchsmartphonetwittercaraccordeonvideoarrowarrowdownloaddownloaduploadsection_scrollerglobemapIcon-Shop-Websitecontactenergyhomebridgeshighrisetunnelmininghousearrow-uparrow-downarrow-leftarrow-leftarrow-circle-rightchevron-right-circleuserexternlinkcartissuuclosekeystarweb

Hovenbrua

Norway

As part of the improvements to European route E6, Norwegian highway FV 755 between Leksvik and Vanvikan has also been upgraded. This narrow and winding 3.4 km long route leads through a tunnel and across several bridge constructions, among them the Hovenbru.

Back

Project data

Year of completion
2011
Project duration
3 Months
Country
Norway
Address
Rv755 20, 7120, Norway
Realization
GRUNNARBEID AS
Structure
Bridge
Type of structure
Composite construction

Bridge deck/superstructure

Shape
Radius
Type of carriage/traveller or formwork
Crane-lifted brackets
Length of bridge (superstructure)
48.88 m
Width of bridge (superstructure)
11.50 m
Height of bridge (up to top edge of superstructure)
6.50 m
Cross-sectional shape of structural steelwork
I-section girder
Clear width of structural steelwork
6
Clear height of structural steelwork
2.29
Length of concreting section
48.88 m
Number of casting sections
1