calldocumentfacebookmessagemypartnerwindowsapplegoogleplayworkerroutecoinspinterestplaysearchsmartphonetwittercaraccordeonvideoarrowarrowdownloaddownloaduploadsection_scrollerglobemapIcon-Shop-Websitecontactenergyhomebridgeshighrisetunnelmininghousearrow-uparrow-downarrow-leftarrow-leftarrow-circle-rightchevron-right-circleuserexternlinkcartissuuclosekeystarweb

Dual-carriageway bridge in Nitra

Slovakia

Work on extending and upgrading the R1 trunk road between the towns of Nitra and Banská Bystrica in Slovakia is progressing apace. To close the last gaps in the new road between Nitra and Selenec, 3 pairs of Doka cantilever forming travellers were fielded to build a 26m wide 3-cell bridge superstructure.

Back

Project data

Year of completion
2011
Project duration
8 Months
Country
Slovakia
Address
Nitra
Town or city
Nitra
Realization
A-Híd Építő Zrt., Hidepitö
Structure
Bridge
Type of structure
Cantilevering

Bridge deck/superstructure

Construction method
Inclined
Cross-sectional shape
Multi-cell box girder – straight webs
Overall length of bridge
356 m
Number of spans
4
Longest span
85 m
Number of piers
2
Length of concreting section
5 m
Number of casting sections
59