calldocumentfacebookmessagemypartnerwindowsapplegoogleplayworkerroutecoinspinterestplaysearchsmartphonetwittercaraccordeonvideoarrowarrowdownloaddownloaduploadsection_scrollerglobemapIcon-Shop-Websitecontactenergyhomebridgeshighrisetunnelmininghousearrow-uparrow-downarrow-leftarrow-leftarrow-circle-rightchevron-right-circleuserexternlinkcartissuuclosekeystarweb
I consent to the use of cookies by this website for analyses and personalized content. Find out more OK
I consent to the use of cookies by this website for analyses and personalized content. Find out more OK

The North Approach Roads - Ada Bridge

Serbia

Construction of the superstructure takes place by a process of successive concreting and pre-stressing "field by field". The range of 35m is bypassed with one yoke at the mid-span and with eight steel grids that bypass the mid-spans between the pylon and the yoke.

Back

Project data

Year of completion
2014
Project duration
12 Months
Country
Serbia
Address
Belgrade
Zip/Postal Code
11000
City, State
Belgrade
Realization
Porr Technobau und Umwelt AG
Structure
Civil engineering
Type of structure
Bridge piers and pylons