calldocumentfacebookmessagemypartnerwindowsapplegoogleplayworkerroutecoinspinterestplaysearchsmartphonetwittercaraccordeonvideoarrowarrowdownloaddownloaduploadsection_scrollerglobemapIcon-Shop-Websitecontactenergyhomebridgeshighrisetunnelmininghousearrow-uparrow-downarrow-leftarrow-leftarrow-circle-rightchevron-right-circleuserexternlinkcartissuuclosekeystarweb
I consent to the use of cookies by this website for analyses and personalized content. Find out more OK
I consent to the use of cookies by this website for analyses and personalized content. Find out more OK

Brenner Base Tunnel - Saxener Tunnel

Austria

For the 'Saxener Tunnel' subsection of the Wolf II contract section of the Brenner Base Tunnel mega-project, Doka supplied a fully customised, all-hydraulic formwork solution complete with assembly by Doka Austria's Pre-assembly Service. The tunnel formwork traveller masters an extremely steep gradient of more than 10 % and pours the concrete for a block length of 10 metres every day.

Back

Project data

Year of completion
2016
Project duration
5 Months
Country
Austria
Realization
Swietelsky Tunnelbau GmbH
Structure
Tunnel

Partially monolithic construction method

Clear width
9.26 m
Clear height
6.87 m
Formed length of tunnel
1000 m
Length of concreting section
10.0 m
Number of casting sections
100
Cycle time
1 -day cycle