calldocumentfacebookmessagemypartnerwindowsapplegoogleplayworkerroutecoinspinterestplaysearchsmartphonetwittercaraccordeonvideoarrowarrowdownloaddownloaduploadsection_scrollerglobemapIcon-Shop-Websitecontactenergyhomebridgeshighrisetunnelmininghousearrow-uparrow-downarrow-leftarrow-leftarrow-circle-rightchevron-right-circleuserexternlinkcartissuuclosekeystarweb
I consent to the use of cookies by this website for analyses and personalized content. Find out more OK
I consent to the use of cookies by this website for analyses and personalized content. Find out more OK

S10 Neumarkt Tunnel

Austria

The Neumarkt Tunnel is another section of the S10 Highway in the Mühlviertel district. As work had to be done with traffic flowing, the Forming wagon was relocated several times. Doing so allowed us to manage the various phases of traffic without any problems. In order to meet the construction schedule's tight deadlines we deployed two Forming wagons at the same time.

Back

Project data

Year of completion
2015
Project duration
24 Months
Country
Austria
Structure
Tunnel
Type of structure
Cut-and-cover tunnel

Wall

Construction method
Partially monolithic
Cross-sectional shape
Curved/round
Clear width
10.10 m
Clear height
7.57 m
Formed length of tunnel
1240 m
Length of concreting section
12.63 m
Number of casting sections
101