calldocumentfacebookmessagemypartnerwindowsapplegoogleplayworkerroutecoinspinterestplaysearchsmartphonetwittercaraccordeonvideoarrowarrowdownloaddownloaduploadsection_scrollerglobemapIcon-Shop-Websitecontactenergyhomebridgeshighrisetunnelmininghousearrow-uparrow-downarrow-leftarrow-leftarrow-circle-rightchevron-right-circleuserexternlinkcartissuuclosekeystarweb
I consent to the use of cookies by this website for analyses and personalized content. Find out more OK
I consent to the use of cookies by this website for analyses and personalized content. Find out more OK

Gomagoi Tunnel

Italy

The 240 m long tunnel was built using the cut-and-cover method. Owing to its tight radii, a 3-part Doka tunnel formwork traveller was used. The traveller was built from SL-1 system components.

Back

Project data

Year of completion
2010
Project duration
12 Months
Country
Italy
Address
Gomagoi, Val Solda
Realization
Mayr Josef & Co. S.a.s.
Structure
Tunnel
Type of structure
Cut-and-cover tunnel

Wall

Construction method
Partially monolithic
Cross-sectional shape
Curved/round
Clear width
5.10 m
Clear height
7.19 m
Formed length of tunnel
240 m
Length of concreting section
12 m
Number of casting sections
20