calldocumentfacebookmessagemypartnerwindowsapplegoogleplayworkerroutecoinspinterestplaysearchsmartphonetwittercaraccordeonvideoarrowarrowdownloaddownloaduploadsection_scrollerglobemapIcon-Shop-Websitecontactenergyhomebridgeshighrisetunnelmininghousearrow-uparrow-downarrow-leftarrow-leftarrow-circle-rightchevron-right-circleuserexternlinkcartissuuclosekeystarweb
I consent to the use of cookies by this website for analyses and personalized content. Find out more OK
I consent to the use of cookies by this website for analyses and personalized content. Find out more OK

Nibelungen Bridge, Regensburg

Germany

Two composite forming carriages were fielded for casting the 30 m wide and 208 m long deck slab of the new Nibelungen Bridge in Regensburg, Bavaria. Due to the cantilevering steel brackets, the formwork- and platform unit was designed so that it could be swung out hydraulically to be repositioned, at the push of a button.

Back

Project data

Year of completion
2004
Project duration
6 Months
Country
Germany
City, State
Regensburg
Realization
Max Bögl GmbH, Neumarkt
Structure
Bridge
Type of structure
Composite construction

Bridge deck/superstructure

Length of bridge (superstructure)
206.90 m
Width of bridge (superstructure)
30 m
Height of bridge (up to top edge of superstructure)
6 m
Cross-sectional shape of structural steelwork
Trough with bracing
Length of concreting section
24 m
Number of casting sections
10
Cycle time
7 -day cycle