calldocumentfacebookmessagemypartnerwindowsapplegoogleplayworkerroutecoinspinterestplaysearchsmartphonetwittercaraccordeonvideoarrowarrowdownloaddownloaduploadsection_scrollerglobemapIcon-Shop-Websitecontactenergyhomebridgeshighrisetunnelmininghousearrow-uparrow-downarrow-leftarrow-leftarrow-circle-rightchevron-right-circleuserexternlinkcartissuuclosekeystarweb
I consent to the use of cookies by this website for analyses and personalized content. Find out more OK
I consent to the use of cookies by this website for analyses and personalized content. Find out more OK

Westbahn Tunnel at Stans

Austria

This 634 m long railway tunnel was built by Alpine Bau GmbH using the cut-and-cover method. A high-performing Doka tunnel slab traveller was in service here for the cover slab, which has a haunched cross-section. Owing to the varying cross-sectional shape, Doka planned an easily adaptable tunnel formwork
traveller that was designed to separate in the middle.

Back

Project data

Year of completion
2009
Project duration
18 Months
Country
Austria
Address
Stans, Tyrol, Austria
Realization
Alpine Bau GmbH
Structure
Tunnel
Type of structure
Cut-and-cover tunnel

Wall

Construction method
Segmented (non-monolithic)
Cross-sectional shape
Rectangular
Clear width
17.08 m
Clear height
8.50 m
Formed length of tunnel
634 m
Length of concreting section
12 m
Number of casting sections
55
Cycle time
7 -day cycle