calldocumentfacebookmessagemypartnerwindowsapplegoogleplayworkerroutecoinspinterestplaysearchsmartphonetwittercaraccordeonvideoarrowarrowdownloaddownloaduploadsection_scrollerglobemapIcon-Shop-Websitecontactenergyhomebridgeshighrisetunnelmininghousearrow-uparrow-downarrow-leftarrow-leftarrow-circle-rightchevron-right-circleuserexternlinkcartissuuclosekeystarweb
I consent to the use of cookies by this website for analyses and personalized content. Find out more OK
I consent to the use of cookies by this website for analyses and personalized content. Find out more OK

Bridge across Örekilsälven River

Sweden

The RC deck slab had a composite cross-section and was cast with the aid of two forming carriages. Each 20 m long and 27 m wide carriage was travelled across the steel superstructure via "frame-type roller-trestle bearing supports – with longitudinal connectors", so that the loads occurring during pouring could be evenly distributed in the webs of the troughs.

Back

Project data

Year of completion
2006
Project duration
18 Months
Country
Sweden
Address
European route E6
City, State
Saltkällan, near Munkedal
Realization
NCC Construction Sverige AB, Gothenburg
Structure
Bridge
Type of structure
Composite construction

Bridge deck/superstructure

Length of bridge (superstructure)
477 m
Width of bridge (superstructure)
24.20 m
Height of bridge (up to top edge of superstructure)
85 m
Cross-sectional shape of structural steelwork
Seal-welded box girder
Parapet height
0.80 m
Length of concreting section
16 m
Number of casting sections
31
Cycle time
7 -day cycle