Office Headquarters for YOUI Insurance located in Sippy Downs
Challenge:
The biggest challenge faced by the client was forming the high decks (5.50m and 4.50m soffits) in a safe and cost effective manner. Productivity was the key factor in the final decision
Solution:
Dokamatic tables with Eurex 20top550 props were ideally suited for the project. The use of the system results in major saving in labour as the tables are supplied fully assembled to site and are safely and efficiently re-located with the Dokart plus shifting appliance
Year of site completion
2017
Country
Australia
City
Sippy Downs, Sunshine Coast
Contractor
TK Formbuild Pty Ltd