calldocumentfacebookmessagemypartnerwindowsapplegoogleplayworkerroutecoinspinterestplaysearchsmartphonetwittercaraccordeonvideoarrowarrowdownloaddownloaduploadsection_scrollerglobemapIcon-Shop-Websitecontactenergyhomebridgeshighrisetunnelmininghousearrow-uparrow-downarrow-leftarrow-leftarrow-circle-rightchevron-right-circleuserexternlinkcartissuuclosekeystarweb
I consent to the use of cookies by this website for analyses and personalised content. Find out more OK
I consent to the use of cookies by this website for analyses and personalised content. Find out more OK

Doka formwork solution delivers one of India’s largest cable stay bridges

22.06.2023 | Press
Doka India has completed work on the 900-metre Dwarka Bridge, providing valuable connectivity within the northwestern region of Gujarat.

Press Contact

Impressions

Doka formwork and engineering solutions have successfully been used to deliver a 900-metre central cable-stayed bridge, including highway approaches. Spanning a length of 2.5 km, the 29.6-metre-wide, four-lane bridge includes 3.5 km of retaining walls, and a 1.42-kilometre approach on either side. Comprised of a composite deck and pylon structure, the total length between the two pylons stretches 500 metres, making it the largest span of any cable stay bridge in India. With the overall structure suspended by 76 cables, the most challenging aspect of the project was the design of the pylons which are curved along a vertical structure, at an angle of 20.1 degrees at the centre, 22.6 degrees to the left and 19 degrees to the right. As such, the formwork solution required a significantly tailored approach, while adhering to the strict engineering requirements of the completed structure.

Based on its knowledge and in-depth proposal, Doka India was awarded the contract to deliver a formwork solution for the two, ‘A’ shaped composite pylons, each reaching a height of 130 metres and located in the open water of the Gulf of Kutch. This challenging project was designed by Yogesh Patil, Doka India Group Leader Engineering and Pramendra Singh, Doka India Project Engineer. The Doka Formwork Instructor team, Ash Narayan Singh and Bijaya Kumar Swain were not only able to find a solution that met the project’s requirement, but furthermore enabled the onsite training for other stakeholders to learn and adapt in a safe manner.

Mr. Singh, commented, “While several of our core products were used in the construction process, our key asset, particularly when it came to the pylons was our Automatic climbing formwork SKE plus. Designed to be completely crane-independent, and fully modular, we were able to work around the unique and complex shape of the pylon, while remaining protected both from the weather and height. As a fully hydraulic system, it also meant that a lot of time could be saved during repositioning.”

As part of the project’s product solution, Doka’s SKE50, SKE100, SKE100 plus, Top 50 and Shaft Platform were used throughout in order to support the timely execution.

Speaking on behalf of the contractor, SP Singla Constructions, Project Manager, Mr. Devinder Singh said, “We’ve been particularly impressed with the work carried out by the Doka team, who has done a wonderful job by designing and guiding the formwork installation for our curved pylon, while simultaneously providing the technical support that has helped to reduce the overall time of each cycle. Thanks to this efficiency, and the diligent training provided to our engineers, foremen and team on site, we’ve managed a smooth and safe operation throughout.”

This could also be of interest for you:

Doka commits to Science Based Targets initiative (SBTi)

03.12.2024 | Press

Developing the Heart of Luyang

01.11.2024 | Press

Do you have any questions on the article? Get in touch with us!

Fields marked with * are required.
* Please complete all required text fields!
    Message was not sent - please try again later.